Done (from April to June)
  • Topographic site survey
  • Selection of architectural team: Root Studio
  • Selection of interior design team: Maison Sarayan
  • Selection of hotel consultant: PMHOSPITALITY
  • Concept Design (Estudo Previo) from architecture and decoration
  • Project Road Map definition
  • Tender of engineering projects with 6 companies for the following areas (Water & Sewage; Electrical & Mechanics; Foundations & structural; Environmental Impact Assessment)
  • Selection of Engineering team: VHM
  • Selection of Environmental Impact Assessment: Antonio Abreu

In progress (from June to July)
  • Licensing project delivered to the RAP (Região Autónoma do Príncipe)
  • Architectural and engineering detailed design. (Projeto de Execução)
  • Environmental Impact Assessment project.

Next stage (from July to September)
  • Conclusion of all detailed design projects.
  • Tender for 5 companies (Portuguese, Angolan and possibly from another country of the Gulf of Guinea)
  • Construction works to start in September.