Done (from April to June)
- Topographic site survey
- Selection of architectural team: Root Studio
- Selection of interior design team: Maison Sarayan
- Selection of hotel consultant: PMHOSPITALITY
- Concept Design (Estudo Previo) from architecture and decoration
- Project Road Map definition
- Tender of engineering projects with 6 companies for the following areas (Water & Sewage; Electrical & Mechanics; Foundations & structural; Environmental Impact Assessment)
- Selection of Engineering team: VHM
- Selection of Environmental Impact Assessment: Antonio Abreu
In progress (from June to July)
- Licensing project delivered to the RAP (Região Autónoma do Príncipe)
- Architectural and engineering detailed design. (Projeto de Execução)
- Environmental Impact Assessment project.
Next stage (from July to September)
- Conclusion of all detailed design projects.
- Tender for 5 companies (Portuguese, Angolan and possibly from another country of the Gulf of Guinea)
- Construction works to start in September.